Architect
BBS Architect
Delivery
Design-Bid-Build
Completed
2022
Work Scope
Work was strategically divided into fifteen (15) phases across the East,
West, and North Wings to maintain daily operations:
• Phases 1, 2, 7 & 8: Renovation of the second-floor areas, including
structural floor infills over existing atriums to create new restrooms
and expanded usable space.
• Phases 3, 4, 9 & 10: Renovation of the first and ground floors, with
work sequenced to maintain plumbing, electrical, and restroom
functionality throughout construction.
• Phases 5, 6, 11 & 12: Completion of the remaining first and ground
floor zones with finish upgrades and infrastructure tie-ins.
• Site Enhancements: Expansion of on-site parking lot with 112
spaces, new landscaping, and a stormwater detention system to
improve site performance and accessibility.
• Phases 13-15: included renovation in the West Wing including
commercial kitchen, dining, new roof patio, and shade structure.
Upgrades to conference center, renovated fitness, wellness and
locker rooms, and the onsite daycare facility.
This phased approach reduced downtime, increased value, and
delivered a renewed workplace aligned with Farm Bureau’s vision for
the future.
“Neumann’s ability to anticipate challenges and proactively address them through collaborative discussions allowed this project to proceed seamlessly and on schedule.”